The Planning

Contractor
The Mobile Bay National Estuary Program has awarded the WMP contract to a consultant, Dewberry Engineers Inc., who will work with Parker-Martin Consulting Group on the public participation activities. 

Project Timeline
The Dewberry Team has prepared a schedule that will result in a final Watershed Management Plan Report being prepared within 12 months.  We recognize the importance of being flexible and adaptable to changing client needs.  We understand that conditions and priorities change over time and that a successful contractor must be able to accelerate activities when requested or adjust to changing priorities. 

  1. April 2015 - November 2015: Watershed Characterization
  2. October 2015 - December 2015: Management Measures
  3. November 2015 - February 2016: Watershed Management Plan Development, Regulatory Evaluation, Implementation of Financing
  4. March 2016: Delivery of Draft Watershed Management Plan
  5. April 2016: Delivery of Final Watershed Management Plan

Project Status
Accomplishments

  1. Reporting Period Ending June 30, 2016
  2. Reporting Period Ending January 29, 2016
  3. Reporting Period October 1, 2015 - December 31, 2015

Meeting Information
Community Outreach Efforts
Meeting 7: March 22, 2016

Meeting 6: November 27, 2015

Meeting 5: October 13, 2015

Meeting 4: August 20, 2015

Meeting 3: July 29, 2015

Meeting 2: July 14, 2015

Meeting 1: July 6, 2015

Watershed Management Plan
Plan currently in development