The Plan

Watershed management Plan
Appendices
Contractor

The Mobile Bay National Estuary Program awarded the WMP contract to a consultant, Dewberry Engineers Inc., who also conducted the public participation activities. 

Project Timeline

The Dewberry Team prepared a schedule that resulted in a final Watershed Management Plan Report being prepared within 12 months.  We recognized the importance of being flexible and adaptable to changing client needs.  We understood that conditions and priorities change over time and that a successful contractor must be able to accelerate activities when requested or adjust to changing priorities. 

  1. January 2013 - December 2013: Outreach and Engagement
  2. January 2013 - May 2013: Watershed Characterization
  3. June 2013 - September 2013: Identification and Analysis
  4. September 2013 - December 2013: Developing the Plan
  5. January 2014 - August 2014: Draft Watershed Management Plan
  6. September 2014: Delivery of Final Watershed Management Plan
Project Status

Accomplishments

  1. Reporting Period Ending March 28, 2014
  2. Reporting Period for September 1, 2013 to February 28, 2014
  3. Reporting Period Ending October 31, 2013
  4. Reporting Period Ending August 31, 2013
  5. Reporting Period for March 30, 2013 to July 26, 2013
  6. Reporting Period for Jauary 7, 2013 to March 29, 2013